Solution  2182294.1 :   How To Replace The Disk Chassis In A ZFS Storage Appliance DE3-24C Or DE3-24P JBOD  


Related Items
  • Oracle Storage DE3-24C
  •  
  • Oracle ZFS Storage ZS5-4
  •  
  • Oracle ZFS Storage ZS5-2
  •  
  • Oracle ZFS Storage ZS4-4
  •  
  • Oracle Storage DE3-24P
  •  
Related Categories
  • PLA-Support>Sun Systems>Sun_Other>Sun Collections>SN-OTH: DISK-CAP VCAP
  •  




In this Document
Goal
Solution


Oracle Confidential PARTNER - Available to partners (SUN).
Reason: This is a FRU so should not be an external Document

Applies to:

Oracle Storage DE3-24P - Version All Versions to All Versions [Release All Releases]
Oracle Storage DE3-24C - Version All Versions to All Versions [Release All Releases]
Oracle ZFS Storage ZS4-4 - Version All Versions to All Versions [Release All Releases]
Oracle ZFS Storage ZS5-2 - Version All Versions to All Versions [Release All Releases]
Oracle ZFS Storage ZS5-4 - Version All Versions to All Versions [Release All Releases]
7000 Appliance OS (Fishworks)

Goal

Replacement of DE3-24C Disk Chassis (Compliance model SE44U) or DE3-24P Disk Chassis (Compliance Model SE42U)

 

Scope: 

For Standalone JBODS and those attached to ZFS ZS4-4, ZS5-2 and ZS5-4 ( cluster included )

Solution

DISPATCH INSTRUCTIONS

- WHAT SKILLS DOES THE FIELD ENGINEER/ADMINISTRATOR NEED?

Training and experience with Oracle DE3-24C / DE3-24P JBOD . This is a Field Replaceable unit, to be performed by a trained Service Personnel.

TIME ESTIMATE: 60 minutes

TASK COMPLEXITY: 2

FIELD ENGINEER/ADMINISTRATOR INSTRUCTIONS:
PROBLEM OVERVIEW: The disk center-plane in the DE3-24P/C tray has been determined faulty and needs to be replaced.
This require the whole tray chassis to be replaced as the center-plane is not considered to be field-replaceable.

WHAT STATE SHOULD THE SYSTEM BE IN TO BE READY TO PERFORM THE RESOLUTION ACTIVITY?:

This Procedure will require the system to be down .

WHAT ACTION DOES THE FIELD ENGINEER/ADMINISTRATOR NEED TO TAKE?:

Bring down and power off the Mini Cluster
Power off the JBOD using the power switch on the back of the JBOD.
Swap JBOD chassis and re-cable, taking care to check all wiring and making sure all components go in to the same positions in the new chassis.

Regulatory Requirement Below:

Verify the Power Supply to be installed in the replacement chassis FRU is mfgr Bel Fuse,P/N GFE580-SBB-5125 (May be followed by suffixes).

The Power supplies listed in the FE handbook meet this requirement.


Label cables and disks before removal --- location of hardware and cables is important when powered back on
Sequence to Power on JBOD and then the Mini Cluster .
Power up JBODs first.
Use the ILOM/SP to check the serial number before starting MIni Cluster.
**** Perform the Serial Number recovery if required . *****
Start the Mini Cluster .
Verify that the Mini cluster has access to the JBOD and all components are optimal .

OBTAIN CUSTOMER ACCEPTANCE
WHAT ACTION DOES THE FIELD ENGINEER/ADMINISTRATOR NEED TO TAKE TO RETURN THE SYSTEM TO AN OPERATIONAL STATE?:

Use the Mini cluster BUI to confirm success

PARTS NOTE:

DE3-24P chassis with midplane part-number: 7319615 [F]

DE3-24C chassis with midplane part-number: 7319616 [F]

REFERENCE INFORMATION: