How to Replace a SPARC S7-2L Clear Plastic Air Duct Assembly [VCAP]
Related Categories |
- PLA-Support>Sun Systems>Sun_Other>Sun Collections>SN-OTH: SPARC-CAP VCAP
- Microlearning>Video>ML-VID-VCAP
|
In this Document
Applies to:
SPARC S7-2L - Version All Versions to All Versions [Release All Releases]
Information in this document applies to any platform.
Goal
How to Replace a SPARC S7-2L Clear Plastic Air Duct Assembly
*******************************************************************************
To report errors or request improvements on this procedure, please add a comment on Doc ID: 2158644.1
*******************************************************************************
ESD Caution:
- Circuit boards and drives contain electronic components that are extremely sensitive to static electricity. Ordinary amounts of static electricity from clothing or the work environment can destroy the components located on these boards. Do not touch the components along their connector edges.
- Use a Antistatic Wrist strap. Attach one end of the strap to your wrist and the other end to the chassis, depending on what type of strap you use, with the adhesive end or the metal plug.
- Use an Antistatic Mat. Place ESD-sensitive components such as motherboards, memory, and other PCBs on an antistatic mat.
Contamination Caution:
- Dust particles of packaging material are number one cause of datacenter contamination. Make sure to remove all packaging material, up to the ESD safe packaging material, while still being outside the datacenter.
Solution
DISPATCH INSTRUCTIONS
WHAT SKILLS ARE REQUIRED?:
No special skills required, Customer Replaceable Unit (CRU) procedure
Time Estimate: 30 minutes
TASK COMPLEXITY: 0
REMOVAL/REPLACEMENT INSTRUCTIONS:
PROBLEM OVERVIEW: SPARC S7-2L Clear Plastic Air Duct Assembly Replacement
WHAT STATE SHOULD THE SYSTEM BE IN TO BE READY TO PERFORM THE RESOLUTION ACTIVITY?:
DAMAGE ALERT: Perform a visual inspection of the replacement part to make sure that there are no damaged components, connectors, bent pins, damaged packages during shipping, etc). If the part is damaged, don't install it into the system, order a new part. Handle with caution and package carefully the return part to avoid any damages during shipping.
Note: A data backup is not a prerequisite but is a wise precaution.
Customer should perform an orderly and graceful shutdown of applications and OS to get the OpenBoot PROM prompt. Then power off the server and remove the AC power cords from the system.
WHAT ACTIONS ARE REQUIRED?:
Remove Clear Plastic Air Duct Assembly
1. Prepare the server for service.
a. Power off the server and disconnect the power cords from the power supplies.
b. Extend the server to the maintenance position in the rack.
c. Attach an antistatic wrist strap to your wrist and then to a metal area on the chassis.
Caution - Components inside the chassis might be hot. Use caution when servicing components inside the chassis.
2. Remove server top cover:
a. Open the server top cover by pressing and holding down the top cover release button and then use the recessed area to slide the top cover toward the rear of the server (about 0.5 inches (12.7 mm)).
b. Lift the top cover off the chassis and set it aside.
3. Remove clear plastic air duct assembly.
Install Clear Plastic Air Duct Assembly
1. Take the new clear plastic air duct assembly and place it over the top of the CPU's and DIMMs allowing the DIMMs to protrude through the open slots and the assembly to fit nicely between the chassis walls, power supply metal casing and mid-wall.
2. Install the server top cover:
a. Place the server top cover on the chassis and slide the top cover toward the front of the server (about 0.5 inches (12.7 mm)) until you hear the top cover release button lock into place.
3. Return the Server to operation.
a. Remove any anti-static measures that were used.
b. Return the server to it's normal operating position within the rack.
c. Re-install the AC power cords and any data cables that were removed.
d. Power on server. Verify that the Power/OK indicator led lights steady on.
OBTAIN CUSTOMER ACCEPTANCE
WHAT ACTIONS ARE REQUIRED TO RETURN THE SYSTEM TO AN OPERATIONAL STATE?:
Boot system and monitor boot sequence for errors. Test functionality of system:
1. Run the Solaris "fmadm faulty" and SP/ILOM "show faulty" command to verify that the fault has been cleared.
2. Perform one of the following tasks based on your verification results:
* If the previous steps did not clear the fault, refer to doc 1004229.1 for information about the tools and methods you can use to diagnose and clear
component faults.
* If the previous steps indicate that no faults have been detected, the component has been replaced successfully. No further action is required
3. Restart software applications per applicable administration guides to resume system operation.
PARTS NOTE:
https://support.oracle.com/handbook_private/Systems/SPARC_S7_2L/components.html#Chassis
REFERENCE INFORMATION:
SPARC S7-2L Service Manual: http://docs.oracle.com/cd/E72363_01/html/E73201/index.html
Attachments
This solution has no attachment