How to Replace a Sun Server X4-2L Coin Cell Battery
Related Items |
- Oracle SuperCluster T5-8 Full Rack
- Exadata X4-2 Hardware
- Big Data Appliance X4-2 Hardware
- Sun Server X4-2L
- Big Data Appliance X4-2 Full Rack
- Exadata X4-2 Quarter Rack
- Oracle SuperCluster T5-8 Half Rack
- Exadata X4-2 Full Rack
- Exadata X4-8 Hardware
- Big Data Appliance X4-2 Starter Rack
- Zero Data Loss Recovery Appliance X4 Hardware
- Exadata X3-8 Hardware
- Exadata X4-2 Half Rack
- Big Data Appliance X4-2 In-Rack Expansion
- Exadata X4-2 Eighth Rack
- Exadata X3-8b Hardware
- Oracle SuperCluster M6-32 Hardware
- Oracle SuperCluster T5-8 Hardware
|
Related Categories |
- PLA-Support>Sun Systems>Sun_Other>Sun Collections>SN-OTH: x64-CAP VCAP
|
Applies to:
Big Data Appliance X4-2 Starter Rack - Version All Versions and later
Big Data Appliance X4-2 Hardware - Version All Versions and later
Exadata X4-2 Eighth Rack - Version All Versions to All Versions [Release All Releases]
Exadata X4-2 Hardware - Version All Versions to All Versions [Release All Releases]
Big Data Appliance X4-2 Full Rack - Version All Versions and later
x86_64
Goal
How to Replace a Sun Server X4-2L Coin Cell Battery.
Solution
DISPATCH INSTRUCTIONS
WHAT SKILLS DOES THE FIELD ENGINEER/ADMINISTRATOR NEED:
No special skills required, Customer Replaceable Unit (CRU) procedure
TIME ESTIMATE: 30 minutes
TASK COMPLEXITY: 0
FIELD ENGINEER/ADMINISTRATOR INSTRUCTIONS:
PROBLEM OVERVIEW: A Sun Server X4-2L Coin Cell Battery needs replacement
WHAT STATE SHOULD THE SYSTEM BE IN TO BE READY TO PERFORM THE RESOLUTION ACTIVITY? :
If the system is still up and functioning, customer should perform an orderly and graceful shutdown of applications and OS. Then power off the server and remove the AC power cords from the system.
A data backup is not a prerequisite but is a wise precaution.
Note:
If this server is part of an Exadata, ZDLRA or SuperCluster, please follow shutdown instructions in DOC ID: 1188080.1
If this server is part of a Big Data Appliance X4-2, please follow shutdown instruction in DOC ID: 2099858.1
WHAT ACTION DOES THE ENGINEER NEED TO TAKE:
1. Prepare the server for service.
- Power off the server and disconnect the power cords from the power supplies.
- Extend the server to the maintenance position in the rack.
- Attach an anti-static wrist strap.
- Remove the top cover.
2. Locate and Remove the Battery.
- The system battery is a 3V Lithium Coin Cell Battery (CR2032 or BR2032) which is located vertically on the system board directly behind PCIe slot 6
- To dislodge the battery from its retainer, gently push the top edge of the battery away from the retainer.
- Lift the battery up and out of its retainer.
3. Install the Replacement Battery.
- Unpackage the replacement battery.
- Press the new battery into the battery retainer with the positive side (+) facing the server chassis side wall.
4. Return the Server to operation
- Replace the top cover
- Remove any anti-static measures that were used.
- Return the server to it's normal operating position within the rack.
- Re-install the AC power cords and any data cables that were removed.
- Power on server.
5. Adjust system clocks if needed
- If the ILOM is not configured to use ntp adjust the time by logging into the ILOM cli and setting the clock using the following command format
-> set /SP/clock datetime=MMDDhhmmYYYY
- When powering on the host for the first time adjust the system date/time by pressing F2 to go into the BIOS setup. The date and time can be adjusted in the "Main" menu section. After setting the time correctly navigate to the "Save&Exit" section and select the "Save Changes and Reset" option.
OBTAIN CUSTOMER ACCEPTANCE
WHAT ACTION DOES THE CUSTOMER NEED TO TAKE TO RETURN THE SYSTEM TO AN OPERATIONAL STATE:
Boot up system and verify full functionality
Note:
If this server is part of an Exadata, ZDLRA or SuperCluster, please follow restart instructions in step 7 of DOC ID: 1188080.1
If this server is part of a Big Data Appliance X4-2, please follow restart instructions in DOC ID: 2099858.1
REFERENCE INFORMATION:
Sun Server X4-2L Documentation
http://docs.oracle.com/cd/E36974_01/index.html
Oracle Integrated Lights Out Manager (ILOM) 3.1 Documentation
http://docs.oracle.com/cd/E24707_01/html/E24528/index.html
Steps to shut down or reboot an Exadata storage cell without affecting ASM (Doc ID 1188080.1)
Steps to Gracefully Shutdown and Power on a Single Node on Oracle Big Data Appliance Prior to Maintenance (Doc ID 2099858.1)
Attachments
This solution has no attachment