Asset ID: |
1-71-1347630.1 |
Update Date: | 2018-05-09 |
Keywords: | |
Solution Type
Technical Instruction Sure
Solution
1347630.1
:
How to Replace a Sun Fire X4170 M2 Power Distribution Board
Related Items |
- Oracle Exalogic Elastic Cloud X2-2 Qtr Rack
- Sun Fire X4170 M2 Server
- Exadata Database Machine X2-2 Qtr Rack
- Oracle Exalogic Elastic Cloud X2-2 One-Eighth Rack
- Oracle Exalogic Elastic Cloud X2-2 Full Rack
- Exadata Database Machine X2-2 Full Rack
- Exadata Database Machine X2-2 Half Rack
- Exadata Database Machine X2-2 Hardware
- Oracle Exalogic Elastic Cloud X2-2 Half Rack
- Oracle Exalogic Elastic Cloud X2-2 Hardware
|
Related Categories |
- PLA-Support>Sun Systems>Sun_Other>Sun Collections>SN-OTH: x64-CAP VCAP
|
In this Document
Oracle Confidential PARTNER - Available to partners (SUN).
Reason: FRU CAP
Applies to:
Sun Fire X4170 M2 Server - Version All Versions and later
Exadata Database Machine X2-2 Hardware - Version All Versions and later
Exadata Database Machine X2-2 Qtr Rack - Version All Versions and later
Exadata Database Machine X2-2 Half Rack - Version All Versions and later
Exadata Database Machine X2-2 Full Rack - Version All Versions and later
Information in this document applies to any platform.
Goal
How to Replace a Sun Fire X4170 M2 Power Distribution Board.
Solution
DISPATCH INSTRUCTIONS
- WHAT SKILLS DOES THE ENGINEER NEED: General Sun X64 Servers Knowledge
- TIME ESTIMATE: 90 minutes
- TASK COMPLEXITY: 1
FIELD ENGINEER INSTRUCTIONS:
- PROBLEM OVERVIEW: Power distribution board Replacement
- WHAT STATE SHOULD THE SYSTEM BE IN TO BE READY TO PERFORM THE RESOLUTION ACTIVITY?:
The Server must be offline and you do not need to remove the motherboard to service the power distribution board
NOTE - 'If this is an Engineered system then the system administrator should prepare the system for service by performing any application related functions required to shutdown the node. This might include but is not limited to performing a system backup, failover of application or services, and finally a system shutdown.'
A data backup is not a pre-requisite but is a wise precaution.
Note: If this server is part of an Exadata, please follow shutdown instructions in Section 1 of DOC ID:
1539451.1
Caution - The server supplies power to the power distribution board even when the server is powered off. To avoid personal injury or damage to the server, you must disconnect the power cords before servicing the power distribution board.
Preparing the server for service.
a. Power off the server and disconnect the power cord (or cords) from the power supply (or supplies).
b. Extend the server to the maintenance position.
c. Attach an antistatic wrist strap.
d. Remove the top cover.
- WHAT ACTION DOES THE ENGINEER NEED TO TAKE:
Removing PDB
1. Disconnect the power supply ribbon cable from the PDB.
2. Disconnect the top cover interlock cable from the PDB.
3. Disconnect the motherboard ribbon cable from the PDB.
4. Remove the four No. 2 Phillips screws securing the PDB to the chassis.
5. Remove the five No. 2 Phillips screws securing the PDB to the bus bar.
6. To disconnect the power distribution board from the connector board, slide the PDB away from the chassis wall.
7. Lift the power distribution board up and out of the chassis.
8. Place the power distribution board on an antistatic mat.
Installing PDB
1. Lower the PDB into the chassis.
2. Slide the PDB toward the chassis wall until it plugs into the connector board.
3. Install five No. 2 Phillips screws to secure the PDB to the bus bar.
4. Install the four No. 2 Phillips screws to secure the PDB to the chassis.
5. Connect the power supply ribbon cable to the PDB.
6. Connect the top cover interlock cable to the PDB.
7. Connect the motherboard ribbon cable to the PDB.
8. Return the server to operation.
a. Install the top cover.
b. Return the server to the normal rack position.
c. Reconnect the power cord (or cords) to the power supply (or supplies) and power on the server. Verify that the AC Present LED is lit.
OBTAIN CUSTOMER ACCEPTANCE
- WHAT ACTION DOES THE CUSTOMER NEED TO TAKE TO RETURN THE SYSTEM TO
AN OPERATIONAL STATE:
Check for full system functionality
Note: If this server is part of an Exadata, please follow restart instructions in Section 1, step 10 of DOC ID:
1539451.1
PARTS NOTE:
https://support.oracle.com/handbook_private/Systems/SunFireX4170_M2/components.html
REFERENCE INFORMATION:
Sun Fire X4170 M2 Server Service Manual
http://download.oracle.com/docs/cd/E19762-01/E22369-02/index.html
How to shutdown the Exadata database nodes and storage cells in a rolling fashion so certain hardware tasks can be performed. (Doc ID 1539451.1)
Attachments
This solution has no attachment