Solution Type Technical Instruction Sure Solution 1333874.1 : How to Remove and Replace a SPARC T3-4 Server Battery:ATR:1333874.1:0
In this Document
Applies to:SPARC T3-4 - Version All Versions to All Versions [Release All Releases]Information in this document applies to any platform. GoalHow to remove and replace a T3-4 Server Battery ********************************************************************************* SolutionDISPATCH INSTRUCTIONS WHAT SKILLS ARE REQUIRED: No special skills required, Customer Replaceable Unit (CRU) procedure Time Estimate: 30 minutes
Task Complexity: 0 REMOVAL/REPLACEMENT INSTRUCTIONS PROBLEM OVERVIEW: How to remove and replace a Battery
WHAT STATE SHOULD THE SYSTEM BE IN TO BE READY TO PERFORM THE RESOLUTION ACTIVITY? : DAMAGE ALERT: Perform a visual inspection of the replacement part to make sure that there are no damaged components, connectors, bent pins, damaged packages during shipping, etc. If the part is damaged, don't install it into the system, order a new part. Handle with caution and package carefully the return part to avoid any damages during shipping.
Take ESD Precautions
WHAT ACTIONS ARE REQUIRED: Remove the System Battery The system battery is a cold-service component that can be replaced by a customer. 1. Slide the main module out of the server
2. Remove the cover from the main module and locate the system battery 3. Push the top edge of the battery against the spring and lift it out of the carrier. Install the System Battery 1. Insert the new system battery in the main module, with the positive side (+) facing out. 2. Install the main module back into the server. 3. If the service processor is configured to synchronize with a network time server using the Network Time Protocol (NTP), the ILOM clock will be reset as soon as the server is powered on and connected to the network. Otherwise, proceed to the next step. 4. If the service processor is not configured to use NTP, you must reset the ILOM clock using the ILOM CLI or the web interface. For instructions, see the Oracle Integrated Lights Out Manager (ILOM) 3.0 Documentation Collection. 5. If the service processor is not configured to use NTP, use the ILOM clock command to set the day and time. The following example sets the date to June 17, 2010, and the timezone to GMT. -> set /SP/clock datetime=061716192010 -> show /SP/clock /SP/clock Targets: Properties: datetime = Wed JUN 17 16:19:56 2010 timezone = GMT (GMT) usentpserver = disabled Commands: cd set show Note - For additional details about setting the ILOM clock, refer to the CLI Procedures Guide for Oracle ILOM. 6. Verify that the new system battery is functioning properly. Verify the System Battery 1. Run ->show /SYS/MB/BAT/V_BAT to check the status of the system battery. In the output, the /SYS/MB/BAT/V_BAT status should be OK, as in the following example. sc> show /SYS/MB/BAT/V_BAT Voltage sensors (in Volts): ------------------------------------------------------------------------------ Sensor Status Voltage LowSoft LowWarn HighWarn HighSoft ------------------------------------------------------------------------------ /SYS/MB/V_+3V3_STBY OK 3.36 3.13 3.17 3.53 3.60 /SYS/MB/V_+3V3_MAIN OK 3.37 3.06 3.10 3.49 3.53 /SYS/MB/V_+5V0_VCC OK 5.07 4.55 4.65 5.36 5.46 /SYS/MB/V_+12V0_MAIN OK 12.10 10.90 11.15 12.85 13.10 /SYS/MB/BAT/V_BAT OK 2.83 -- 2.69 . . . sc> show /SYS/MB/BAT/V_BAT Voltage sensors (in Volts): ------------------------------------------------------------------------------ Sensor Status Voltage LowSoft LowWarn HighWarn HighSoft ------------------------------------------------------------------------------ /SYS/MB/V_+3V3_STBY OK 3.36 3.13 3.17 3.53 3.60 /SYS/MB/V_+3V3_MAIN OK 3.37 3.06 3.10 3.49 3.53 /SYS/MB/V_+5V0_VCC OK 5.07 4.55 4.65 5.36 5.46 /SYS/MB/V_+12V0_MAIN OK 12.10 10.90 11.15 12.85 13.10 /SYS/MB/BAT/V_BAT OK 2.83 -- 2.69 . . . OBTAIN CUSTOMER ACCEPTANCE WHAT ACTIONS ARE REQUIRED TO RETURN THE SYSTEM TO AN OPERATIONAL STATE: Verify functionality, no service LEDs or messages
PARTS NOTE: REFERENCE INFORMATION: SPARC T3-4 Server Service Manual: http://docs.oracle.com/cd/E19417-01/pdf/E20813.pdf See also Oracle Integrated Lights Out Manager (ILOM) 3.0 Documentation http://docs.oracle.com/cd/E19860-01/index.html Attachments This solution has no attachment |
||||||||||||||
|