Solution  1316240.1 :   How to Replace a Sun Fire X4270 M2 Power Distribution Board  


Related Items
  • SPARC SuperCluster T4-4
  •  
  • Exadata Database Machine X2-2 Qtr Rack
  •  
  • SPARC SuperCluster T4-4 Half Rack
  •  
  • Exadata Database Machine X2-8
  •  
  • Exadata Database Machine X2-2 Full Rack
  •  
  • SPARC SuperCluster T4-4 Full Rack
  •  
  • Sun Fire X4270 M2 Server
  •  
  • Big Data Appliance Hardware
  •  
  • Exadata Database Machine X2-2 Half Rack
  •  
  • Exadata Database Machine X2-2 Hardware
  •  
Related Categories
  • PLA-Support>Sun Systems>Sun_Other>Sun Collections>SN-OTH: x64-CAP VCAP
  •  




In this Document
Goal
Solution
References


Oracle Confidential PARTNER - Available to partners (SUN).
Reason: fru cap

Applies to:

Exadata Database Machine X2-8 - Version All Versions and later
SPARC SuperCluster T4-4 - Version -Not Applicable- and later
SPARC SuperCluster T4-4 Half Rack - Version -Not Applicable- and later
SPARC SuperCluster T4-4 Full Rack - Version -Not Applicable- and later
Exadata Database Machine X2-2 Hardware - Version All Versions and later
Information in this document applies to any platform.

Goal

How to Replace a Sun Fire X4270 M2 Power Distribution Board.

Solution

DISPATCH INSTRUCTIONS

WHAT SKILLS DOES THE FIELD ENGINEER/ADMINISTRATOR NEED?:
Sun Fire X4270 M2 Training

TIME ESTIMATE: 90 minutes

TASK COMPLEXITY: 1

FIELD ENGINEER/ADMINISTRATOR INSTRUCTIONS:

PROBLEM OVERVIEW: A Sun Fire X4270 M2 Power Distribution Board needs replacement

WHAT STATE SHOULD THE SYSTEM BE IN TO BE READY TO PERFORM THE RESOLUTION ACTIVITY? :

Customer should perform an orderly and graceful shutdown of applications and OS
A data backup is not a pre-requisite but is a wise precaution

Note:

If this server is part of an Exadata, please follow shutdown instructions in DOC ID: 1188080.1

If this server is part of a Big Data Appliance, please follow shutdown instruction in DOC ID: 2099858.1

 

WHAT ACTION DOES THE ENGINEER NEED TO TAKE:
You do not need to remove the motherboard to service the power distribution board
Caution - The server supplies power to the power distribution board even when the server is powered off. To avoid personal injury or damage to the server, you must disconnect the power cords before servicing the power distribution board.
1. Prepare the server for service.
   a. Power off the server and disconnect the power cord (or cords) from the power supply (or supplies).
   b. Extend the server to the maintenance position.
   c. Attach an antistatic wrist strap.
   d. Remove the top cover.

Removing the power distribution board
1. Disconnect the power supply ribbon cable from the PDB.
2. Disconnect the top cover interlock cable from the PDB.
3. Disconnect the motherboard ribbon cable from the PDB.
4. Remove the four No. 2 Phillips screws securing the PDB to the chassis.
5. Remove the five No. 2 Phillips screws securing the PDB to the bus bar.
6. To disconnect the power distribution board from the connector board, slide the PDB away from the chassis wall.
7. Lift the power distribution board up and out of the chassis.
8. Place the power distribution board on an antistatic mat.

Installing the power distribution board
1. Lower the PDB into the chassis.
2. Slide the PDB toward the chassis wall until it plugs into the connector board.
3. Install five No. 2 Phillips screws to secure the PDB to the bus bar.
4. Install the four No. 2 Phillips screws to secure the PDB to the chassis.
5. Connect the power supply ribbon cable to the PDB.
6. Connect the top cover interlock cable to the PDB.
7. Connect the motherboard ribbon cable to the PDB.
8. Return the server to operation.
  a. Install the top cover.
  b. Return the server to the normal rack position.
  c. Reconnect the power cord (or cords) to the power supply (or supplies) and power on the server. Verify that the AC Present LED is lit.

OBTAIN CUSTOMER ACCEPTANCE

WHAT ACTION DOES THE CUSTOMER NEED TO TAKE TO RETURN THE SYSTEM TO AN OPERATIONAL STATE:

Boot up system and verify full functionality

Note:

If this server is part of an Exadata, please follow restart instructions in step 7 of DOC ID: 1188080.1

If this server is part of a Big Data Appliance, please follow restart instructions in DOC ID: 2099858.1


PARTS NOTE:

Sun Fire X4270 M2 Server Service Manual
http://download.oracle.com/docs/cd/E19245-01/
Steps to shut down or reboot an Exadata storage cell without affecting ASM (Doc ID 1188080.1)
Steps to Gracefully Shutdown and Power on a Single Node on Oracle Big Data Appliance Prior to Maintenance (Doc ID 2099858.1)