1310675.1
:
How to Remove and Replace a Starcat System Control Peripheral Board Power Cable:ATR:1541:2
Related Items |
- Sun Fire E25K Server
- Sun Fire 15K Server
- Sun Fire 12K Server
- Sun Fire E20K Server
|
Related Categories |
- PLA-Support>Sun Systems>Sun_Other>Sun Collections>SN-OTH: SPARC-CAP VCAP
|
In this Document
Oracle Confidential PARTNER - Available to partners (SUN).
Reason: FRU CAP
Applies to:
Sun Fire E20K Server - Version Not Applicable and later
Sun Fire 12K Server - Version Not Applicable and later
Sun Fire 15K Server - Version Not Applicable and later
Sun Fire E25K Server - Version Not Applicable and later
Information in this document applies to any platform.
Goal
How to remove and replace a Starcat System Control Peripheral Board Power Cable
Solution
CAP PROBLEM OVERVIEW: System control peripheral board power cable needs replacement.
DISPATCH INSTRUCTIONS
WHAT SKILLS DOES THE ENGINEER NEED:
Starcat Training, Familiarity with SMS command set
TIME ESTIMATE: 30 minutes
FIELD ENGINEER INSTRUCTIONS
WHAT STATE SHOULD THE SYSTEM BE IN TO BE READY TO PERFORM THE RESOLUTION ACTIVITY? :
Customer should fail-over to the OTHER SC and disable SMS failover
Preparation:
Note: Before shutting down and replacing an SC make sure that clock from the other SC to all components is in a good state. To check this run "showboards -c" command for SMS 1.4 and later. ( See *Document ID: 1006413.1 Check clock status before replacement of System controller for more information )
As user sms-svc (or another user with platform privileges), verify:
- that the other SC is MAIN (showfailover -r)
- that the other SC is the current clock source (showboards -c)
- that failover is disabled (showfailover)
- shut down SC with faulty drive ("init 0"), then power it off from the main using "poweroff scX"
Physical Replacement:
- Unseat the SC board. SCs have been known to automatically power on, which can cause problems during this procedure.
- Remove the SC Peripheral board (the tape drive and DVD drive are externally visible here).
- Replace the power board cable
- IMPORTANT: Insert the SCPER board FIRST, then insert the SC board LAST.
Poweron spare SC:
- "poweron scX"
- Observe boot sequence, ensure no errors appear
- Wait for SMS to start, then enable failover "setfailover on"
OBTAIN CUSTOMER ACCEPTANCE: N/A
WHAT ACTION DOES THE CUSTOMER NEED TO TAKE TO RETURN THE SYSTEM TO AN OPERATIONAL STATE: N/A
REFERENCE INFORMATION:
Service Manual: http://download.oracle.com/docs/cd/E19065-01/servers.e25k/index.html
Attachments