Solution Type  Technical Instruction Sure

Solution  1303338.1 :   M8000 M9000 How to Replace a XSCF_B Cold Replacement:ATR:1878:2  


Related Items
  • Sun SPARC Enterprise M9000-64 Server
  •  
  • Sun SPARC Enterprise M9000-32 Server
  •  
  • Sun SPARC Enterprise M8000 Server
  •  
Related Categories
  • PLA-Support>Sun Systems>Sun_Other>Sun Collections>SN-OTH: SPARC-CAP VCAP
  •  




In this Document
Goal
Solution


Oracle Confidential INTERNAL - Do not distribute to customer (OracleConfidential).
Reason: FRU CAP

Applies to:

Sun SPARC Enterprise M8000 Server - Version Not Applicable and later
Sun SPARC Enterprise M9000-32 Server - Version Not Applicable and later
Sun SPARC Enterprise M9000-64 Server - Version Not Applicable and later
Information in this document applies to any platform.

Goal

CAP PROBLEM OVERVIEW: Replace M8000/9000 XSCF_B - Cold replacement
********************************************************************************
To report errors or request improvements on this procedure,
please go to http://support.us.oracle.com and put a comment on Doc ID: 1303338.1
********************************************************************************

Solution

DISPATCH INSTRUCTIONS

WHAT SKILLS DOES THE ENGINEER NEED:(IS A SITE ENGINEER AVAILABLE?)
The engineer should be M8000/M9000 trained

TASK COMPLEXITY: 2

TIME ESTIMATE: 150 minutes

FIELD ENGINEER INSTRUCTIONS

WHAT STATE SHOULD THE SYSTEM BE IN TO BE READY TO PERFORM THE RESOLUTION ACTIVITY? :

A data backup is not a pre-requisite but is a wise precaution.
The customer should conduct an orderly software system shutdown.

Then power down the system.

WHAT ACTION DOES THE ENGINEER NEED TO TAKE:

Cold replacement with power down is required

1. Customer should perform an orderly shutdown of the domains.
2. Change the mode switch setting on the operator panel from Locked to Service.
3. From a console that is connected to XSCF, log in to XSCF, and execute the poweroff -a command.
4. Confirm that the power-off processing is completed by confirming that the POWER LED (green) on the operator panel is off.
5. Switch off all main line switches for the AC section (ACS) in the power supply system.

Note: On a M9000 with an expansion cabinet the base cabinet should be switched off first then the expansion cabinet.
6. Remove the XSCFU to be replaced. Place the removed XSCFU on an antistatic conductive mat.
7. Insert the replacement XSCFU

Note: FE should connect to XSCF serial port in order to gather POST and XCP startup output. In case of unexpected FRU behavior data should be uploaded into the SR 


8. Switch on all main line switches for the AC section (ACS) in the power supply system.

Note: On a M9000 with an expansion cabinet the expansion cabinet should be switched on first then the base cabinet.
9. Confirm that the XSCF STANDBY LED (green) on the operator panel remains lit. If it is blinking, wait until it remains lit.
10. Update the XSCF firmware.
11. Set the XSCF clock with setdate -s MMDDhhmmCCYY.ss
12. Start (turn on power) all domains together

Caution !! When the maintenance work is completed, be sure to confirm the mode switch setting and return the switch to Locked.

OBTAIN CUSTOMER ACCEPTANCE

WHAT ACTION DOES THE CUSTOMER NEED TO TAKE TO RETURN THE SYSTEM TO AN OPERATIONAL STATE:

Check full functionality has been retained

Confirm hardware by running the following commands:
XSCF> showhardconf -M
XSCF> showstatus

PARTS NOTE:

None

REFERENCE INFORMATION:
Service Manual: http://download.oracle.com/docs/cd/E19415-01/index.html